When excavation meets Tetris

Groundforce Shorco_Supplied

A partnership finds solutions for a complex excavation at a new housing development in North Yorkshire.

Contractor East Rudland Construction is carrying out the groundworks and civil engineering for the construction of 25 homes for developer Gem Construction Ltd. One of its tasks is the installation of a stormwater attenuation tank – a large underground reservoir to store rainwater and prevent surcharges into the nearby watercourses during periods of high rainfall. The attenuation tank is a large void made using ACO’s StormBrixx HD900 geocellular blocks encased within an impermeable 1mm LLDPE/HDPE membrane.

“Ground conditions on the site are very challenging,” says Steve Hayhurst, Co-Owner of East Rudland Construction. “The site has a very high water table, which raises the risk of the groundwater floating the tank and lifting it out of the ground.” To prevent this happening, it was necessary to increase the depth of soil on top of the buried tank to hold it down. “We couldn’t bury the tank any deeper, so instead we had to change its shape.”

Therefore, the tank had to be redesigned, reducing its height by approximately one metre to allow a greater depth of fill on top. However, to maintain the same volume, the tank’s footprint had to be extended outwards to make up for the reduction in depth. Because of site constraints, this meant the redesigned tank was an irregular shape to occupy the space that was available.

Groundforce Shorco_Supplied_216556

East Rudland Construction used Groundforce Shorco to support the sides of the oddly shaped excavation

Irregular excavation

To support the sides of the oddly shaped excavation, East Rudland Construction used Groundforce Shorco. It used its modular Mega Brace system to support a steel sheet-piled retaining wall and braced with MP50 and MP150 hydraulic props. The system is designed so that beams of virtually any length can be assembled using the modular sections in different combinations.

However, this excavation’s complex shape meant that certain lengths of the perimeter frame were little more than one metre in length – too short even for standard equipment. So Groundforce Shorco modified the lengths to suit the application. To support the sides of the 3m-deep excavation, it supplied 170 lightweight GFI interlocking steel piles, each 6m in length.

Larssen piles would normally have been the default option, but site constraints ruled this out, explains Hayhurst: “Larssen piles are strong, heavy-duty sheet piles with a deep U-shaped cross section and we would have struggled to remove them after completion of the excavation without resorting to a larger excavator. We couldn’t use a heavy excavator without risking damage to the installed tank.

“There was also very limited space in which to manoeuvre a large machine. Therefore, we had to find an alternative. We used about 170 6m-long GFIs to stop water flow into the excavation. GFIs are interlocking sheets offering a lighter option than the Larssen piles. They are much easier to remove from the ground.”

So the lightweight GFI piles could be driven to the correct depth, East Rudland Construction pre-augured the perimeter of the excavation, loosening the soil and allowing insertion of the sheet piles.

Another requirement was to carry out extensive frame-to-sheet-pile welding to prevent lateral movement of the frame. The irregular shape of the excavation meant there were numerous short lengths of frame subject to relatively high end-loads. Welding the frame to the sheet piles helped ensure rigidity.

“We did all the installation ourselves, using our own plant and equipment, but we relied heavily on the design and technical support provided by Groundforce Shorco,” says Hayhurst. “The job started out as a potential headache but together we found a solution and made it work smoothly.”

Follow East Rutland Construction at b.link/CABE_ERC
Find out more about Groundforce Shorco at b.link/Groundforce_Shorco

Jobs

Permanent

Quantity Surveyor

Site based Quantity Surveyor role South Birmingham £45-55,000 24 days holiday plus bank holidays ...

Permanent

Senior Quantity Surveyor

Senior Quantity Surveyor Social Housing Planned Maintenance Sector Location: Ongar Are you a skill...

Permanent

Quantity Surveyor (Roofing & Cladding)

Quantity Surveyor - Roofing & CladdingQuantity Surveyor - a leading specialist contractor is searchi...

Permanent

Building Control Surveyor

Hiredonline Consultancy Ltd
Level: 2A 3H/G Salary: £40,000 - £65,000 (DOE) plus car allowance Location: North West of England ...